SECURING BUILDING PERMIT STEPS

Issuance of Building permit

ABOUT THE SERVICE

All person, firm or corporation including any agency or instrumentality of the Government wanting
to be done must first obtain a building permit from the building official of the Office of the City Engineer, 2nd floor,
City Hall Annex Building, Zamboanga City.

1. Duly accomplished Application Forms
( ) Building Permit (Form 1)
( ) Electrical Permit (Form 2)
( ) Sanitary Permit (Form 3)
( ) Mechanical Permit (Form 4)
2. If the applicant is the registered lot owner
( ) Certified true copy of the Transfer Certificate of Title (TCT)
( ) Tax Declaration
( ) Current Real property Tax Receipt
3. If applicant is not registered lot owner
( ) Duly Notarized Copy of the Contract of Lease or
( ) Duly notarized copy of Deed of absolute sale or
( ) Duly notarized Copy of sale
( ) Authorization from the lot owner (Duly Notarized)
4. Minimum of (5) Five sets of standard plans and specifications prepared, signed and sealed
( ) By a duly Licensed Architect or Civil Engineer (Architectural or Structural Plans)
( ) By a duly Licensed Sanitary Engineer or Master Plumber (Plumbing or Sanitary Plans)
( ) By a duly Licensed professional Electrical Engineer (Electrical Plans)
( ) By a duly Licensed professional Mechanical Engineer (Mechanical Plans)
( ) Detailed Estimate of the project, Signed and sealed by a duly licensed Architect or Engineer
5. Structural analysis and Design Computation for two (2) Storey and up.
6. Boring and Load Test for three (3) Strorey and up.
7. Fire Safety evaluation clearance, from the Bureau of Fire Protection
8. Estimated Cost of the Project (Prepared, Signed and Sealed by a Duly Licensed Architect or Engineer)
9. Locational Clearance from the City Planning and Development Office
10. Certificate of approval from DOLE (Safety Management Program).
11. And other clearance if necessary.

SECURING BUILDING PERMIT STEPS

 

Issuance of Certificate of Occupancy

ABOUT THE SERVICE

That no building/structure shall be used until the Building Official has issued a Certificate of Occupancy therefor.
R E Q U I R E M E N T S
1. Copy of the Approved Building Forms
( ) Building Permit
( ) Electrical Permit
( ) Sanitary Permit
( ) Mechanical Permit
2. Certificate of Completion ( Civil, Electrical , Sanitary and Mechanical )
3. Copy of the Approved Building Plans and Specifications
4. Copy of the Building Permit Fees and Fire Safety Inspection Certificate fee
5. Fire Safety Inspection Certificate for All types of Occupancy
6. Log Book sheet for Three (3) Storey Building and up.

 

Schedule of fees